New CLEC Timeline
CompanyServicesIndustry LinksBill AuditingNew CLEC GuidesContact
PlanningNew CLEC TimelineAgreementsCodes Required

 This timeline is not intended to be an all-inclusive list and is based on "best case" scenario, not actual time. I recommend allowing six months to get everything set up in the first LATA and two to three months for each additional LATA you enter after that.

 Weeks

A

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

Identify target markets

x

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Generate business plan

x

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

CLEC certification

x

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Interconnection agreement

x

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Arrange Code Administrator

 

x

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

OCN from NECA

 

O

D

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

FRN from FCC

 

x

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

ACNA from NECA

 

O

D

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Arrange, fitup switch location

 

 

S

x

x

x

x

x

F

 

 

 

 

 

 

 

 

 

 

 

 

Decide on switch type

 

 

 

x

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Contact LEC Account Manager

 

 

 

x

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Order ILEC colos (UNE-L)

 

 

 

O

x

x

x

x

x

x

x

x

x

x

x

x

D

 

 

 

 

If you don't start out using a CMDS provider, order non-hosted RAO code from Telcordia

 

 

 

 

O

D

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

If you start out using a CMDS provider, arrange agreement with CMDS provider and obtain RAO code from them

 

 

 

 

S

x

x

F

 

 

 

 

 

 

 

 

 

 

 

 

 

File first FCC Form 499-A, obtain TRS #

 

 

 

 

S

F

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Order Switch CLLI from Telcordia

 

 

 

 

x

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Arrange userID for NAS, PAS

 

 

 

 

x

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Submit NRUF to NANPA

 

 

 

 

 

x

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Obtain forms, applications from LEC

 

 

 

 

 

x

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Arrange SS7 provider and sign up for LIDB, CNAM, CLASS and 800 services from SS7 provider

 

 

 

 

 

O

x

x

D

 

 

 

 

 

 

 

 

 

 

 

 

Order Point Codes

 

 

 

 

 

x

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Arrange OS/DA provider

 

 

 

 

 

x

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Arrange AOCN (if not code admin)

 

 

 

 

 

x

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Submit Pooling forecast (PAS)

 

 

 

 

 

x

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Order LRN NXX

 

 

 

 

 

O

x

x

x

x

x

x

x

x

x

D

 

 

 

 

 

Order switch

 

 

 

 

 

 

O

x

x

x

x

D

 

 

 

 

 

 

 

 

 

Notify SS7 provider of your point code and Destination Point Codes of the LEC offices you are trunking to

 

 

 

 

 

 

x

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Sign NPAC agreement

 

 

 

 

 

 

S

 F

 

 

 

 

 

 

 

 

 

 

 

 

 

Arrange SOA provider

 

 

 

 

 

 

 

x

 

 

 

 

 

 

 

 

 

 

 

 

 

Review codes for NXX inputs with AOCN

 

 

 

 

 

 

 

x

 

 

 

 

 

 

 

 

 

 

 

 

 

Input switch record into BIRRDS

 

 

 

 

 

 

 

x

 

 

 

 

 

 

 

 

 

 

 

 

 

Input LRN NXX into BIRRDS

 

 

 

 

 

 

 

x

 

 

 

 

 

 

 

 

 

 

 

 

 

Verify SPID has been added to NPAC

 

 

 

 

 

 

 

x

 

 

 

 

 

 

 

 

 

 

 

 

 

Request SOA provider to issue orders for LRN and full NXX block

 

 

 

 

 

 

 

x

 

 

 

 

 

 

 

 

 

 

 

 

 

Order other NXXs

 

 

 

 

 

 

 

O

x

x

x

x

x

x

x

D

 

 

 

 

 

Create tracking log for codes

 

 

 

 

 

 

 

x

 

 

 

 

 

 

 

 

 

 

 

 

 

Joint Planning Meeting with ILEC

 

 

 

 

 

 

 

x

 

 

 

 

 

 

 

 

 

 

 

 

 

Submit CLEC profile

 

 

 

 

 

 

 

x

 

 

 

 

 

 

 

 

 

 

 

 

 

Submit ntwk interconn.sheets to ILEC

 

 

 

 

 

 

 

x

 

 

 

 

 

 

 

 

 

 

 

 

 

Submit trunk forecast to LEC

 

 

 

 

 

 

 

x

 

 

 

 

 

 

 

 

 

 

 

 

 

Submit SS7 certification forms to LEC if SS7 provider is NOT the LEC

 

 

 

 

 

 

 

x

 

 

 

 

 

 

 

 

 

 

 

 

 

Submit E911 forms to LEC

 

 

 

 

 

 

 

x

 

 

 

 

 

 

 

 

 

 

 

 

 

Meet with 911 coordinators from each county to discuss default PSAP / ESN, surcharge rates, surcharge reimbursements and ALI database requirements

 

 

 

 

 

 

 

x

 x

 

 

 

 

 

 

 

 

 

 

 

 

Set up and test ALI database updates

 

 

 

 

 

 

 

 

S

F

 

 

 

 

 

 

 

 

 

 

 

Connect to ASR system

 

 

 

 

 

 

 

 

S

F

 

 

 

 

 

 

 

 

 

 

 

Insert Additional Homing Records into BIRRDS

 

 

 

 

 

 

 

 

 

x

 

 

 

 

 

 

 

 

 

 

 

Input NXXs into BIRRDS via AOCN

 

 

 

 

 

 

 

 

 

x

 

 

 

 

 

 

 

 

 

 

 

Verify thousand blocks were added to NPAC

 

 

 

 

 

 

 

 

 

x

 

 

 

 

 

 

 

 

 

 

 

Order SS7 A links if LEC is provider

 

 

 

 

 

 

 

 

 

 

O

x

x

x

D

 

 

 

 

 

 

SS7 Certification Testing with LEC if a third party provider is involved

 

 

 

 

 

 

 

 

 

 

 

S

x

x

x

F

 

 

 

 

 

Order EF and muxed DS1 for ancillary trunks

 

 

 

 

 

 

 

 

 

 

 

O

x

x

x

x

D

 

 

 

 

Order backhaul to colos

 

 

 

 

 

 

 

 

 

 

 

O

x

x

x

x

x

D

 

 

 

CIC from NANPA

 

 

 

 

 

 

 

 

 

 

 

O

D

 

 

 

 

 

 

 

 

Order OS/DA trunks to provider

 

 

 

 

 

 

 

 

 

 

 

 

O

x

x

x

x

D

 

 

 

Order E911 trunks, activate

 

 

 

 

 

 

 

 

 

 

 

 

O

x

x

x

x

D

 

 

 

Order, turn up initial LIS trunks

 

 

 

 

 

 

 

 

 

 

 

 

O

x

x

x

x

D

 

 

 

Install switch hardware

 

 

 

 

 

 

 

 

 

 

 

 

S

F

 

 

 

 

 

 

 

Connect to LSR system

 

 

 

 

 

 

 

 

 

 

 

 

 

x

 

 

 

 

 

 

 

Initial switch translations

 

 

 

 

 

 

 

 

 

 

 

 

 

 

S

F

 

 

 

 

 

Test trunks

 

 

 

 

 

 

 

 

 

 

 

 

 

 

S

x

x

F

 

 

 

Install collocated terminals

 

 

 

 

 

 

 

 

 

 

 

 

 

 

x

 

 

 

 

 

 

Turn up OS/DA

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

S

F

 

 

 

Make test calls to each  test number from various carriers to ensure other carriers have added your NXXs in their routing tables correctly, issue trouble tickets to carriers

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

x

 

 

 

Cut over switch

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

x

 

 

Cut over subscribers at colos

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

x

 

CDR records to billing provider

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 x+

CABS records to CABS biller

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

x+

Notify Pooling Administrator that LRN NXX is now in service

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

x

Submit Part 4 form to Code Admin

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

x

    Updated 8/10/06

    Key:

 

 

     A = Ahead of Time

     O = Order    D = Deliver

     S = Start     F = Finish

 